We anticipate that our construction will be complete by January-February of 2025. As we move forward, we will continue to update you and let you know if we are still on track to reveal the new spaces by this timeline.
Our work continues on the 2nd floor addition. Here is a brief update on progress:
-
Exterior: The brick facade is 95% complete. Windows are being installed currently. The roof is mostly complete, we are waiting on delivery of metal trim to be installed at the edge of the roof.
-
Interior: Electrical wiring and mechanicals are being installed now. Most of the interior walls have been framed. The carpenters have begun sheetrock installation. Steel stairs are being installed.
-
Some of the exterior scaffolding has been taken down. Until the end of the job scaffold will remain on the exterior to protect the emergency exit doors.
-
The elevator installation should be starting within the next two weeks.
-
Interior finishes including paint, cabinets, bathrooms and ceilings will be starting very soon.
-
As of right now we are still on schedule for occupancy in early to mid February of 2025.
-
Furniture for the new classrooms and office spaces has been selected.
-
The contractors will be restoring the blacktop in the back including stencils and the small playground after the interior work is finished.
-
Our cafeteria is now complete, with additional space. We are waiting for the order of some new lunchroom tables.